15th VCM Report recaps progress at Vogtle expansion through June 2016
Thursday, Sep 01, 2020
Georgia Power today filed its 15th Vogtle Construction Monitoring (VCM) Report with the Georgia Public Service Commission (PSC). The company files a VCM report every six months to recap the latest progress in the construction of Plant Vogtle Units 3 and 4. Today’s report highlights multiple construction milestones in the first half of 2016 and requests approval of $141 million invested by Georgia Power during that time. The Georgia PSC has unanimously approved all costs submitted through the VCM process to date.
The new Vogtle units are among the first built in the U.S. in the last three decades and, once online, will serve customers for more than 60 years. The expansion of Plant Vogtle is also the state’s largest job-producing construction project with more than 6,000 workers on site today and 800 permanent jobs once the new units begin operation.
Progress outlined in today’s report includes:- Performed 6.9 million work hours safely from January to June 2016 with all construction activities meeting stringent Nuclear Regulatory Commission (NRC) requirements.
- Placed thousands of tons of modules, including the CA02 and CA03
structural modules for Unit 3 – the two modules complete the placement
of the “Big Six” modules for the unit.
- Installed or placed more than 1,480 tons of rebar, more than 2,451
tons of structural steel and more than 10,845 cubic yards of concrete in
the nuclear islands, turbine islands and annex building alone.
- Completed all Vogtle Unit 1 230-kV switchyard modifications
necessary to connect the new units to the transmission grid without
interrupting power delivery from the operational units.
- Transitioned Westinghouse and its affiliates as the primary contractor, which has enhanced communication.
The capital and construction cost for Georgia Power’s share of the new units remains $5.44 billion with projected in-service dates of June 2019 (Unit 3) and June 2020 (Unit 4). The 15th VCM Report continues to illustrate that completing the new units at Plant Vogtle remains the best cost option for meeting Georgia’s future energy needs. The projected overall peak rate impact of the Vogtle nuclear expansion continues to be 6 to 8 percent – nearly half of the original peak rate forecast – due to lower financing rates, other benefits the company has proactively pursued and the fuel savings of nuclear. Most of the rate impact is already included in rates, with approximately 2.5 percent remaining to be added over the next three years. Once the new units come on line, they are expected to put downward pressure on rates and deliver long-term savings for Georgia customers.
Georgia Power delivers reliable energy for customers at the lowest possible cost by leveraging a diverse generation mix, including nuclear, 21st century coal and natural gas, as well as renewables such as solar and wind.
About Georgia PowerGeorgia Power is the largest subsidiary of Southern Company (NYSE: SO), one of the nation’s largest generators of electricity. Value, Reliability, Customer Service and Stewardship are the cornerstones of the company’s promise to 2.5 million customers in all but four of Georgia’s 159 counties. Committed to delivering clean, safe, reliable and affordable energy at rates below the national average, Georgia Power maintains a diverse, innovative generation mix that includes nuclear, 21st century coal and natural gas, as well as renewables such as solar, hydroelectric and wind. Georgia Power focuses on delivering world-class service to its customers every day and the company is consistently recognized by J.D. Power and Associates as an industry leader in customer satisfaction.
For more information, please visit :
https://www.georgiapower.com